Electricity Connection

PERMANENT / TEMPORARY ELECTRICITY CONNECTION


1

Prescribed application form will be available.

Information/Facilitation Counter at Palika Kendra and at the Office of Executive Engineer (Distribution), Palika Kendra, on all working days between 10.00 a.m. and 1.00 p.m.
For North of Rajpath-Room No. 1813, Palika Kendra
For South of Rajpath-Kidwai Nagar (West).

 

These forms can be downloaded from NDMC's website:- www.ndmc.gov.in  

a) For North of Rajpath - Room No.1813, Palika Kendra  

b) For South of Rajpath - Kidwai Nagar (West) 

2.

Applications for electric connection will be received.

In the Office of the Executive Engineer (Distribution) Palika Kendra for North of Rajpath and at Kidwai Nagar (West) for South of Rajpath.

3.

Acknowledgement of receipt of application form with required documents will be issued.

Within 3 days.

4.

Scrutiny of Application form.

Within 15 days of application.

5.

Information about deficiencies in application form.

Within 20 days of application.

6.

Sanction of load by NDMC/Competent authority.

Within 30 days of submission of form complete in all respects fulfilling all the formalities.

7.

Estimate for providing service cable and meter board and its sanction.

15 days after sanction of load.

8.

Execution of work of providing meter board and service cable in the premises of the consumers.

Within 45 days of the deposit of amount.

9.

Release of connection.

Within 15 days of submission of agreement form and deposit of security amount and completion of all formalities.

Application form is available "Click Here"